Estimating Aid Sheet

Non-Prevailing Wage

The following is an estimating aid sheet for non-prevailing wage work. The estimations take into account, pump cost per yard, standard mixes, and standard hose.


Quantity

10 yards
20 yards
30 yards
40 yards
50 yards
60 yards
70 yards
80 yards
90 yards
100 yards

Price

$390.00
$490.00
$590.00
$690.00
$790.00
$890.00
$990.00
$1,090.00
$1,190.00
$1,290.00

Cost Per Yard Pumped

$39.00
$24.50
$19.67
$17.25
$15.80
$14.83
$14.14
$13.63
$13.22
$12.90

Estimators: please be careful not to overlook any projects with limited access which may require additional hose requirements on a regular basis.
Pumping 10 yards with an additional 100ft. of system for a total of 300ft. will incur an average cost per yard of $59.00
In cases of greater amounts of hose or lesser volume and/or slower pour times upwards of 1 hour or more per load, I have tracked average costs per yard pumped as high as $60.00 - $100.00.
For pours requiring excess travel, 4000+ PSI, Lightweight, or Sand Slurries, Rock volumes over 35%, and prevailing wage projects, please refer to the appropriate rate sheets.



3/8 Pea Gravel Concrete Pumps | License #: 753191 | Fully Insured | Commercial | Industrial | Residential | Cell (310) 261-6509 | Office (562) 906-2007